In response to the national "Belt and Road" and "21st Century Maritime Silk Road" initiatives, our company has actively adopted a "going global" strategy, establishing a full industrial chain layout encompassing road engineering subcontracting, bitumen materials, and bitumen equipment. The Philippines, as an important node along the Maritime Silk Road, has seen continuous growth in road infrastructure construction in recent years. Therefore, our company has vigorously developed the Philippine market.
The client is a leading construction company in the Dumaguete region. Their existing stationary asphalt plant could no longer meet capacity and environmental requirements. To support their business expansion, they purchased our MAP1500 Mobile Asphalt Mixing Plant. Since its commissioning, the plant has operated stably for 1,440 hours (180 days).
In late August 2026, our company dispatched sales personnel and two engineers to the Dumaguete site for a scheduled return visit and inspection. The client expressed satisfaction with the performance of our product. Firstly, it resolved the difficult issue of permit approval. Local environmental regulations are very strict, leading to complex approval procedures for constructing stationary asphalt plants. The design of our mobile asphalt plant effectively addressed this challenge. Secondly, the entire plant features a modular design, requiring no foundation and enabling rapid installation and commissioning, saving the client significant manpower, material resources, and costs.
![]() |
Location: Dumaguete, Philippines Model: MAP1500 Mobile Asphalt Mixing Plant Capacity: 120 tons/hour Commissioning Date: March 2026 |
During the return visit, several issues were also identified:
Our engineers promptly studied and provided effective solutions for the above issues:
(1) Recommended that the client install rain shelters above the graded aggregate bins to prevent rainwater from soaking the aggregates.
(2) Cleaned and adjusted the powder pipelines, promptly removing residual material. Advised operators to perform daily cleaning and adjust the operational sequence.
(3) Regarding the client's feedback on insufficient powder supply, recommended installing an additional feeder. This single measure alone saves the client $3,000 per month in cement procurement costs. After a week of on-site review and inspection, we resolved the existing problems, ensured the efficient operation of the asphalt plant, and strengthened the bond between our company and the client.
The successful commissioning of this site not only provides strong technical support for local road construction but also represents a crucial step in our company's "going global" strategy. Moving forward, we will use this as a foothold to expand across the entire Southeast Asia region, contributing to road construction efforts there and safeguarding the long-term development of our company.